The Tees Valley combined authority has asked construction firms to advise on how its proposed £1bn transport programme should be packaged for procurement, having submitted a five-year wish-list to the Department for Transport. The authority wants industry feedback on the most effective way to structure the work before it settles its procurement strategy.
The programme is set to run from April 2027 to March 2032 and covers major road schemes, railway upgrades, bus infrastructure, active travel and transport technology. The government has already confirmed £978m of core transport funding for the region, but the wider list includes projects that still require further business case approvals and additional financial backing. The authority has acknowledged that delivering the full programme will depend on government support and potentially further outside funding.
Major schemes proposed
The headline projects on the list are:
- the Darlington Northern Link Road;
- upgrades to the A66 and A689 corridors;
- a new platform at Middlesbrough Station;
- redevelopment of Thornaby Station.
Further ambitions include a new station at Teesside International Airport, improvements to Middlesbrough bus station and transport links serving the Teesworks development.
Funding caveat
Steve Harker, the combined authority's cabinet member for transport and infrastructure, said it was crucial people understood that major transport schemes often require significant additional funding even where the body is devolved. Government backing for the plans was therefore vital, he said, because it would allow external bodies to help fund the programme and give the region the best chance of delivering as many projects as possible in good time.
Procurement and supplier engagement
Despite the funding uncertainties, the authority is pressing ahead with early supplier engagement to prepare its procurement strategy. It expects to let multiple contracts covering highways, rail, civil engineering and specialist infrastructure rather than award one giant deal. It is also considering a programme-wide alliance based on the FAC-1 Framework Alliance Contract model, which would bring delivery partners together and is intended to encourage regional contractors and SMEs to participate.
For suppliers, that structure would split work by discipline — highways, rail, civil engineering and specialist infrastructure — instead of concentrating it in a single large award, with the alliance option under review aimed at widening participation beyond the largest contractors.
An initial supplier launch event was held on 9 November, and firms are now invited to provide feedback through a market engagement questionnaire. Contractors have until 1 March 2027 to respond.